Our customer required a new gully, complete with new pipe runs and new chamber, for a boiler discharge.


We cut straight lines in the concrete, and proceeded to break out the area. Once broken out we carried out the excavation works down to a suitable depth for sufficient fall on the new pipework. We installed the gully and surrounded in concrete, then connected the new pipe run and fed into the newly constructed chamber.



From the new chamber we carried out a second excavation to the existing chamber and laid a new pipe, connecting on both ends. Once connected we reinstated inside the existing chamber and proceeded to back fill and compact up to existing levels. We then reinstated the areas by relaying the turf and laying new concrete to existing levels, once completed all works we cleared site and left in a clean and tidy manner.



 
 
 